Tierra Linda/CLC/Mariposa Campus Rebuild Project

Tierra Linda/CLC/Mariposa Campus Rebuild Project

Two Week Look Ahead

3/5/2018 through 3/18/2018 

Week of March 5th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the CLC Modular Classrooms
    • GrowthPoint continues to work on completing work in the modules such as HVAC, Electrical and Plumbing
    • Continue MEP connections to site utilities by Alten
    • Start vent wells and other site work at Buildings A and D
    • Interior finishes
    • Continue structural weld and set of Building B first floor modules

Week of March 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

  • Activities at the CLC Modular Classrooms
    • Complete weld Building B, first floor modules
    • Make ready for Building B second floor modules delivery and set
    • Interior MEP by GrowthPoint
    • Interior finishes
    • Continue MEP connections to site utilities by Alten
    • Continue vent wells and site work at Buildings A and D

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net.