Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 6/4/2018 through 6/17/2018

Tierra Linda/CLC/Mariposa Campus Rebuild Project

Two Week Look Ahead

6/4/2018 through 6/17/2018

 

Week of June 4th - Work Hours: 8:00 a.m. - 6:00 p.m.

Activities:  

  • Activities at the CLC modular classrooms
    • Install Gypcrete on second floor classrooms
    • Continue to form and pour sidewalks
    • Complete bio-swales
    • GrowthPoint continues to work on completing work in the modules such as HVAC, Electrical and Plumbing
    • Continue MEP connections to site utilities by Alten
    • Fire Sprinkler
    • Interior finishes
    • Casework installation continues
    • Deliver and set modular elevator

Week of June 11th - Work Hours: 8:00 a.m. - 6:00 p.m.

Activities:

  • Activities at the CLC modular classrooms
    • Complete electrical connections and energize units
    • Continue forming and pouring concrete flatwork
    • Complete casework
    • Gypcrete in second floor classrooms
    • Epoxy floors in restrooms
    • Continue structural steel decks and stairs
    • Continue modular elevator work
    • Start floor coverings

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net.