Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

4/3/2017 through 4/16/2017

Week of April 3rd                                                                                             Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

  • Activities at the new Learning Commons will include:
    • Continue framing (north, south, common walls and roof walls) and roof
    • Stage and install roof decking materials
    • Continue fire suppression system (sprinklers)
    • Continue MEP rough-in
    • Install windows and hollow metal door frames
    • Complete canopy steel
  • Activities at Modular Multi-Use Room Building
    • Begin painting interior
    • Continue plaster finish coat with integral color
    • Remove scaffolding
    • Site electrical
  • CLC mod classrooms
    • Survey and stake
    • Layout footings
    • Begin grading north east slope, weather permitting
  • Site Development
    • Set rails at west switchback stairs
    • Set pedestrian bridge

Saturday, April 8th – No Work

Sunday, April 9th – No Work           

Week of April 10th                                                                                                                         Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include:
    • Finish miscellaneous framing and blocking
    • Install decking
    • Continue with fire suppression system
    • Continue MEP rough in
    • Continue with windows and hollow metal (HM) door frames
    • Install exterior flashings
    • Erect scaffolds
  • Activities at Modular Multi-Use Room Building
    • Stucco color coat cure
    • Continue interior paint
    • Start electrical/fire alarm and data trim
    • Site Electrical
  • CLC Modular Classrooms
    • Layout and begin to excavate footings
    • Grade slope near parking lot and GP                                                                                                                    

Saturday, April 15th  – No Work

Sunday, April 16th – No Work

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, rwa01@earthlink.net