Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

6/5/2017 through 6/19/2017

Week of June 5th – Work Hours: 8:00 a.m. – 6:00 p.m.

 Activities:  

  • Activities at the new Learning Commons will include
    • Continue with GWB
    • Roofing insulation and start standing seam metal roof
    • Continue with plaster scratch and brown coats
  • Activities at Modular Multi-Use Room Building
    • Interior complete
    • Punch list
    • Sidewalks (depending on new design and P and Q buildings)
  • Activities at the CLC modular classrooms
    • Continue to install rebar and anchor bolts in footings
    • Start rebar installation
    • Site utilities
  • Activities at Mariposa
    • DSA Back check
    • Survey new lunch area

Saturday, June 10th and Sunday, June 11th – No Work

Week of June 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include:
    • Continue GWB
    • Plaster cure and color coat
    • Continue roofing
    • Begin glazing
  • Activities at Modular Multi-Use Room Building
    • Exterior sidewalks and asphalt
    • Tie in Rain Water leaders and storm drain
  • CLC Modular Classrooms
    • Continue footings, imbeds, rebar and inspection

Saturday, June 17th and Sunday, June 18th – No Work

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net