Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

6/12/2017 through 6/25/2017

 

Week of June 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include
    • Continue with insulation and installing and finishing GWB
    • Start interior painting
    • Roofing insulation and standing seam metal roof
    • Plaster color coat
  • Activities at Modular Multi-Use Room Building
    • Interior complete
    • Punch list complete
    • Sidewalks (depending on new design and P and Q buildings)
  • Activities at the CLC modular classrooms
    • Continue to install rebar and anchor bolts in footings
    • First concrete pour
    • Site utilities
  • Activities at Mariposa
    • DSA Back check 

Saturday, June 17th and Sunday, June 18th – No Work

Week of June 19th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities

  • Activities at the new Learning Commons will include:
    • Continue GWB tape and texture
    • Interior painting and finishes
    • Epoxy floors
    • Begin glazing
  • Activities at Modular Multi-Use Room Building
    • Exterior sidewalks and asphalt
    • Tie in Rain Water leaders and storm drain
  • CLC Modular Classrooms
    • Pour footings and stem walls

Saturday, June 24th and Sunday, June 25th – No Work

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net.