Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

5/15/2017 through 5/29/2017

 

Week of May 15th                                                                                                                                                Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include
    • Complete low voltage
    • Start wall insulation and stock GWB
    • Begin metal roof insulation
    • Install window and interior doorframes
    • Start plaster scratch and brown coats
  • Activities at Modular Multi-Use Room Building
    • Restroom toilet partitions
    • Continue VCT flooring
    • Sidewalks (depending on new design and P and Q buildings)
  • Activities at the CLC modular classrooms
    • Continue excavate footings
    • Site utilities

Saturday, May 20th and Sunday, May 21st                                                                                                     No Work

Week of May 22nd                                                                                                                                                Work Hours: 8:00 a.m. – 6:00 p.m.

 

Activities:  

  • Activities at the new Learning Commons will include:
    • Continue GWB
    • Plaster cure
    • Continue roofing
  • Activities at Modular Multi-Use Room Building
    • Exterior asphalt and bio-swale
    • Site electrical
  • CLC Modular Classrooms
    • Continue footings, start footings pour, if submittals are approved
    • Continue utilities

Saturday, May 27th, Sunday, May 28 and Monday, May 29th (Memorial Day Holiday)                No Work

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net.