Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

3/27/2017 through 4/9/2017

Week of March 27th                                                                                          Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

  • Activities at the new Learning Commons will include:
    • Complete framing (north, south, common walls and roof walls) and roof
    • Stage decking materials
    • Shear wall framing and sheeting
    • Continue fire suppression system (sprinklers)
    • Continue MEP rough-in
    • Continue installation of windows and hollow metal door frames
  • Activities at Modular Multi-Use Room Building
    • Tape and finish GWB
    • Install plaster finish coat with integral color
    • Install canopies
    • Interior finishes
    • Begin electrical trim
    • Site electrical
  • CLC mod classrooms
    • Survey and stake
    • Layout footings
    • Begin grading slope, weather permitting
  • Site Development
    • Form and pour stairs and landing at west switchback
    • Set pedestrian bridge
    • Back fill against walls and stairs

Saturday, April 1st and Sunday, April 2nd                                                                     No Work                                                       

 Week of April 3rd                                                                                                                       Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include:
    • Finish miscellaneous framing and blocking
    • Install decking
    • Continue with fire suppression system
    • Continue MEP rough in
    • Continue with windows and hollow metal (HM) door frames
    • Install exterior flashings
    • Erect scaffolds
  •  Activities at Modular Multi-Use Room Building
    • Stucco color coat cure
    • Interior paint
    • Interior finishes
    • Electrical/fire alarm and data trim
    • Site Electrical
  • CLC Modular Classrooms
    • Layout and begin to excavate footings
    • Grading slope

Saturday, April 8th and Sunday, April 9th                                                                      No Work

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, rwa01@earthlink.net