Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

5/8/2017 through 5/21/2017

 

Week of May 8th                                                                                                                                                 Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include
    • Continue framing pick-up/punch lists
    • Continue roofing membrane
    • Install window and interior doorframes
    • Finish lath/start stucco
  • Activities at Modular Multi-Use Room Building
    • Restroom fixtures
    • VCT flooring
    • Side walks
    • Site electrical
  • Activities at the CLC modular classrooms
    • Continue to grade pads and excavate footings
    • Site utilities

Saturday, May 13th and Sunday, May 14th                                                                                                    No Work

 

Week of May 15th                                                                                                                                            

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include:
    • Stock and start wall insulation
    • Continue plaster coats
    • Continue roofing
  • Activities at Modular Multi-Use Room Building
    • Exterior asphalt and bio-swale
    • Site electrical
  • CLC Modular Classrooms
    • Pour footings
    • Continue utilities

 

Saturday, May 20th and Sunday, May 21st                                                                                                    No Work

 Note: Site utilities subcontractor was on site Sunday, April 30th. This was not scheduled or noted in our last newsletter. Subcontractor failed to communicate that he would be working on Sunday. We apologize for any inconvenience. 

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net.