Tierra Linda /CLC/ Mariposa Campus Rebuild Project

Two Week Look Ahead

10/9/2017 through 10/22/2017

Week of October 9th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons:
    • Perimeter fencing
    • Punch Lists
  • Activities at TL Classrooms:
    • Perimeter fencing
    • Punch Lists
  • Activities at the CLC Modular Classrooms:
    • Site work
    • Waterproof foundations
    • Weld modular connections
  • Activities at new Mariposa Upper Play Area:
    • Install basketball backboards
    • Start new walk around parking lot to P buildings
    • Start new safety fence

Week of October 16th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

  • Activities at the new Learning Commons:
    • Punch Lists
  • Activities at TL Classrooms:
    • Punch Lists
  • CLC Modular Classrooms:
    • Continue assembly and finish of modular (Building A)
    • Waterproofing foundation stem walls
    • Site grading
  • Activities at new Mariposa Upper Play Area:
    • Safety fence pedestrian bridge and installation of new gate to Wild Zone

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, or rwa01@earthlink.net