Tierra Linda/CLC Campus Rebuild Project

Two Week Look Ahead

3/20/2017 through 4/2/2017

Week of March 20th                                                                                                                                                            Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

  • Activities at the new Learning Commons will include:
    • Complete framing (north, south, common walls and roof walls) and roof
    • Stage decking materials
    • Shear wall framing and sheeting
    • Continue fire suppression system (sprinklers)
    • Continue MEP rough-in
    • Continue installation of windows and hollow metal door frames
  • Activities at Modular Multi-Use Room Building
    • Tape and finish GWB
    • Install plaster finish coat with integral color
    • Install canopies
    • Site electrical
  • Site Development
    • Form and pour stairs and landing at west switchback
    • Set pedestrian bridge

Saturday, March 25th                                                                                                                                                             No Work

Sunday, March 26th                                                                                                                                                                No Work

                                                                                                                                          

Week of March 27th                                                                                                                                                           Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

  • Activities at the new Learning Commons will include:
    • Finish miscellaneous framing and blocking
    • Install decking
    • Begin fire suppression system
    • Continue MEP rough in
    • Continue with windows and hollow metal (HM) door frames
  • Activities at Modular Multi-Use Room Building
    • Finish GWB, tape and texture
    • Interior finishes
    • Site Electrical
  • Site Development
    • Install handrails at west stairs

Saturday, April 1st                                                                                                                                                                                  No Work                 

Sunday, April 2nd                                                                                                                                                                   No Work                                                                                                                                                                                                                                         

If you have questions please contact the SCSD Project Owner’s Representative, Ralph Adams at 650-218-0888, rwa01@earthlink.net