Learning Spaces

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 2/19 – 3/4/18

Tierra Linda/CLC/Mariposa Campus Rebuild Project
 Two Week Look Ahead
 2/19/18 through 3/4/2018
 

Week of February 19th – Work Hours: 8:00 a.m. – 6:00 p.m.

Monday, February 19th is a Non Work Day – Presidents’ Holiday

Activities:  

Activities at the CLC Modular Classrooms

Work on completing site work such as HVAC, Electrical and Plumbing in the buildings by […]

February 15th, 2018|Learning Spaces|

Final Preliminary Endangerment Assessment (PEA Project Code 204278)

Final Preliminary Endangerment Assessment
(PEA PROJECT CODE 204278)
The San Carlos School District has completed a Preliminary Endangerment Assessment (PEA) related to the recent (2015-2016) expansion and renovation of the Central Middle School-Arroyo School campus. The PEA entailed soil sampling and waste removal done under the oversight of the California Department of Toxic Substances Control […]

February 13th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 2/12/2018 through 2/25/2018

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead
2/12/2018 through 2/25/2018
Week of February 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the CLC Modular Classrooms

Permanently weld and set second floor of Building D
Continue MEP connections to site utilities
Interior finishes

Week of February 19th – Work Hours: 8:00 a.m. […]

February 9th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 2/5-2/18/18

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead
2/05/2018 through 2/18/2018
Week of February 5th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the CLC Modular Classrooms:

Permanently weld and set second floor of Building D
Begin all MEP connections to site utilities

 

Week of February 12th – Work Hours: 8:00 a.m. – […]

February 2nd, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 1/29/18-2/11/18

PENDING WEATHER CONDITIONS – ANTICIPATE HEAVY CONSTRUCTION THIS WEEKEND
Saturday, January 27th and Sunday, January 28th are Work Days – Work Hours: 9:00 a.m. – 5:00 p.m.
 
Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead
1/29/2018 through 2/11/2018
 

Week of January 29th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the CLC Modular Classrooms:

[…]

January 26th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 1/22/18 – 2/4/18

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead
1/22/2018 through 2/04/2018
 

Week of January 22nd – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the CLC Modular Classrooms:

Interior finishes
Prepare Building A for second floor delivery 

Week of January 29th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the CLC Modular […]

January 17th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 1/15/18 – 1/28/18

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
1/15/2018 through 1/28/2018
 

Week of January 15th – Work Hours: 8:00 a.m. – 6:00 p.m.

Monday, January 15th is a Non-Work Day

Activities:  

Activities at the CLC Modular Classrooms:

Interior finishes
Prepare Building A for second floor delivery 

Week of January 22nd – Work Hours: 8:00 a.m. – 6:00 […]

January 17th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 1/8/18-1/21/18

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead  
1/8/2018 through 1/21/2018
Week of January 8th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at TL Classrooms:

Punch Lists

Activities at the CLC Modular Classrooms:

Interior completion of Building D
Weld and secure Building A, make ready for next delivery 

Week of January15th – Work […]

January 5th, 2018|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 12/25/17- 1/7/18

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead
12/25/2017 through 1/7/2018
 
Week of December 25th – Work Hours: 8:00 a.m. – 6:00 p.m.
 Monday, December 25th is a Non-Work Day
Activities:  

Activities at TL Classrooms:

Punch Lists
New Fire Alarm

Activities at the CLC Modular Classrooms:

Interior completion of Building A (by Growth Point)
Deliver and […]

December 20th, 2017|Learning Spaces|

Tierra Linda/CLC/Mariposa Campus Rebuild Project Construction Update for 12/18/17-12/31/17

Tierra Linda/CLC/Mariposa Campus Rebuild Project
Two Week Look Ahead  
12/18/2017 through 12/31/2017
 

Week of December 18th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at TL Classrooms:

Punch Lists
New Fire Alarm

Activities at the CLC Modular Classrooms:

Interior completion of Building D (by Growth Point) 

Week of December 25th – Work Hours: 8:00 a.m. […]

December 19th, 2017|Learning Spaces|