Tierra Linda/CLC Construction Update 5/1/17 – 5/14/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/1/2017 through 5/14/2017
Week of May 1st                                                                                                                                                                    Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Continue framing pick-up/punch lists
Continue roofing membrane
Install window frames
Finish lath/start plaster

Activities at Modular Multi-Use Room Building

Continue […]

April 27th, 2017|Learning Spaces|

Background Narrative and Timeline – Facilities Master Plan (FMP)

I want to invite you to read a new document written and compiled by District Staff. This helpful narrative and timeline was written for parents and community members to learn more about the planning and implementation processes pertaining to our Facilities Master Plan. This document is meant to give context and background […]

April 26th, 2017|Blog, Learning Spaces, News|

Tierra Linda/CLC Campus Construction Update 4/24 – 5/7/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
4/24/2017 through 5/7/2017
 

Week of April 24th                                                                                             

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Finish framing pick-up/punch lists
Continue roofing membrane
Install window frames
Begin plaster

Activities at Modular Multi-Use Room Building

Continue ceramic tile
[…]

April 21st, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update 3/27-4/9/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/27/2017 through 4/9/2017
Week of March 27th                                                                                          Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Stage decking materials
Shear wall framing and sheeting
Continue fire suppression system […]

March 31st, 2017|Learning Spaces|

Mariposa School Meetings Presentation

Here is the presentation that was presented at the Mariposa meetings on March 21 & 22, 2017.

 

March 22nd, 2017|Learning Spaces|

Construction Update for Tierra Linda/CLC Campus Rebuild Project for 3/20-4/2/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/20/2017 through 4/2/2017
Week of March 20th                                                                                                                                                            Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Stage decking materials
Shear wall framing and sheeting
Continue […]

March 16th, 2017|Learning Spaces|

Message And Update From Superintendent Regarding TL/CLC/Mariposa Campus

Here is a message sent to the TL/CLC/Mariposa community on Monday, March 13, 2017
* * *
 

Dear Tierra Linda, Charter Learning Center and Mariposa Community,

Last Friday, we wrote you regarding the significant delays the Campus Rebuild Project (http://www.scsdk8.org/tlclcmariposa-campus-rebuild-project-construction-schedule-update/ ) was facing due to issues with the review process of the Department of State Architecture (DSA). […]

March 15th, 2017|Learning Spaces|

TL/CLC/Mariposa Campus Rebuild Project Construction Schedule Update

3/10/2017

Dear Tierra Linda, Charter Learning Center and Mariposa community,

Last night, our School Board received an update regarding the TL/CLC/Mariposa Campus Rebuild Project. The presentation focused on the fact that there have been significant delays due to the Department of State Architecture (DSA) project review process.

We expect the Mariposa renovations, the TL modernization, the TL […]

March 13th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 3/13 – 3/26/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/13/2017 through 3/26/2017
 

Week of March 13th                                                                                                                                           Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Continue sheeting wall and start roof sheeting
Stage decking materials
[…]

March 10th, 2017|Learning Spaces|

Tierra Linda/CLC Construction Update for 3/6-3/19/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/6/2017 through 3/19/2017
Week of March 6th                                                                                                                                              Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Continue framing (north, south and roof walls) and roof
Set Glue Lamb beams
Stage decking materials
Continue welding structural steel
Set […]

March 2nd, 2017|Learning Spaces|