Learning Spaces

Mariposa School Meetings Presentation

Here is the presentation that was presented at the Mariposa meetings on March 21 & 22, 2017.

 

March 22nd, 2017|Learning Spaces|

Construction Update for Tierra Linda/CLC Campus Rebuild Project for 3/20-4/2/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/20/2017 through 4/2/2017
Week of March 20th                                                                                                                                                            Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Stage decking materials
Shear wall framing and sheeting
Continue […]

March 16th, 2017|Learning Spaces|

Message And Update From Superintendent Regarding TL/CLC/Mariposa Campus

Here is a message sent to the TL/CLC/Mariposa community on Monday, March 13, 2017
* * *
 

Dear Tierra Linda, Charter Learning Center and Mariposa Community,

Last Friday, we wrote you regarding the significant delays the Campus Rebuild Project (http://www.scsdk8.org/tlclcmariposa-campus-rebuild-project-construction-schedule-update/ ) was facing due to issues with the review process of the Department of State Architecture (DSA). […]

March 15th, 2017|Learning Spaces|

TL/CLC/Mariposa Campus Rebuild Project Construction Schedule Update

3/10/2017

Dear Tierra Linda, Charter Learning Center and Mariposa community,

Last night, our School Board received an update regarding the TL/CLC/Mariposa Campus Rebuild Project. The presentation focused on the fact that there have been significant delays due to the Department of State Architecture (DSA) project review process.

We expect the Mariposa renovations, the TL modernization, the TL […]

March 13th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 3/13 – 3/26/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/13/2017 through 3/26/2017
 

Week of March 13th                                                                                                                                           Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Continue sheeting wall and start roof sheeting
Stage decking materials
[…]

March 10th, 2017|Learning Spaces|

Tierra Linda/CLC Construction Update for 3/6-3/19/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/6/2017 through 3/19/2017
Week of March 6th                                                                                                                                              Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Continue framing (north, south and roof walls) and roof
Set Glue Lamb beams
Stage decking materials
Continue welding structural steel
Set […]

March 2nd, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update 2/27 – 3/12/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
2/27/2017 through 3/12/2017
 

Week of February 27th                                                                                     

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Continue framing (north, south and roof walls)
Set Glue Lamb beams
Roof framing
Stage decking materials
Continue welding structural steel
Set […]

February 27th, 2017|Learning Spaces|

Outdoor Learning Space Master Plan

UPDATE (March 1, 2017):  The April 3, 2017 has been postponed.  In the meantime the District now is considering a series of meetings at each site on this topic.  Please stay tuned for more details to come.  

 

The District will be working this year towards developing an Outdoor Learning Space Master Plan. This plan […]

February 6th, 2017|Blog, Learning Spaces, News|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 2/6-2/19/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
2/6/2017 through 2/19/2017
Week of February 6th                                                                                             

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Outside activities at the new Learning Commons will include:

Continue framing (north, south and roof walls)
Set steel columns and install nailers
Lay out for MEP on slab
Pour canopy footings

Outside activities at Modular […]

February 2nd, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project for 1/30 – 2/12/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
1/30/2017 through 2/12/2017
Week of January 30th                                                                                            

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Outside activities at the new Learning Commons will include:

Activities delayed due to rain, however, the overall project is still on schedule
Continue framing (north, south and roof walls)
Survey structural steel anchor bolts
Set […]

January 27th, 2017|Learning Spaces|