Learning Spaces

Tierra Linda/CLC Campus Rebuild Project Construction Update for 8/28/17 through 9/10/17

Saturday August 26th is a Work Day – Work Hours: 9:00 a.m. – 5:00 p.m.

Week of August 28th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Exterior landscaping

Activities at TL Classrooms will include:

Exterior landscaping

Activities at the CLC modular classrooms will include:

Pour […]

August 23rd, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 8/14/17 – 8/27/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
8/14/2017 through 8/27/2017
 

Saturday, August 12th is a Work Day – Work Hours: 9:00 a.m. – 5:00 p.m.

Sunday, August 13th is a Work Day – Work Hours: 9:00 a.m. – 5:00 p.m.

 

Week of August 14th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the […]

August 11th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 8/7/17-8/20/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
8/7/2017 through 8/20/2017
 

Saturday, August 5th is a Work Day – Work Hours: 9:00 a.m. – 5:00 p.m.

Week of August 7th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Floor Prep
Windows and glazing
Concrete Flatwork

Activities at […]

August 3rd, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 7/10 – 7/23/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
7/10/2017 through 7/23/2017
 

Saturday, July 8th is a Work Day – Work Hours: 9:00 a.m. – 5:00 p.m.

Week of July 10th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Interior painting
MEP trim
Ceiling grid
Epoxy floors
Exterior […]

July 7th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 7/3 – 7/16/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
7/3/2017 through 7/16/2017
 

This Saturday July 1st is a work day: Grading

Week of July 3rd – Work Hours: 8:00 a.m. – 6:00 p.m.

July 4th Holiday – No Work

Activities:  

Activities at the new Learning Commons will include:

Interior painting
MEP trim
Ceiling grid
Epoxy floors
Exterior […]

June 30th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 6/26/17 – 7/9/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
6/26/2017 through 7/9/2017
 

Week of June 26th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue finishing GWB
Interior painting
Epoxy floors and ceramic tile
Exterior painting
Remove scaffold and start finish grading
Metal siding
Windows and glazing

[…]

June 21st, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 6/12/17 – 6/25/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
6/12/2017 through 6/25/2017
 

Week of June 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue with insulation and installing and finishing GWB
Start interior painting
Roofing insulation and standing seam metal roof
Plaster color coat

Activities at […]

June 8th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 5/22 – 6/4/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/22/2017 through 6/4/2017
 

Week of May 22nd 

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue with GWB
Metal roofing insulation
Start roofing
Continue with window and door frames
Continue with plaster scratch and brown coats

Activities at Modular Multi-Use […]

May 19th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 5/15/17 – 5/29-17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/15/2017 through 5/29/2017
 

Week of May 15th                                                                                                                                                Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Complete low voltage
Start wall insulation and stock GWB
Begin metal roof insulation
Install window and interior doorframes
Start plaster […]

May 12th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Construction Update for 5/8/17-5/21/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/8/2017 through 5/21/2017
 

Week of May 8th                                                                                                                                                 Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue framing pick-up/punch lists
Continue roofing membrane
Install window and interior doorframes
Finish lath/start stucco

Activities at Modular Multi-Use Room Building

[…]

May 9th, 2017|Learning Spaces|