Tierra Linda/CLC Campus Rebuild Project Construction Update for 6/26/17 – 7/9/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
6/26/2017 through 7/9/2017
 

Week of June 26th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue finishing GWB
Interior painting
Epoxy floors and ceramic tile
Exterior painting
Remove scaffold and start finish grading
Metal siding
Windows and glazing

[…]

June 21st, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 6/12/17 – 6/25/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
6/12/2017 through 6/25/2017
 

Week of June 12th – Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue with insulation and installing and finishing GWB
Start interior painting
Roofing insulation and standing seam metal roof
Plaster color coat

Activities at […]

June 8th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 5/22 – 6/4/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/22/2017 through 6/4/2017
 

Week of May 22nd 

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue with GWB
Metal roofing insulation
Start roofing
Continue with window and door frames
Continue with plaster scratch and brown coats

Activities at Modular Multi-Use […]

May 19th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Project Construction Update for 5/15/17 – 5/29-17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/15/2017 through 5/29/2017
 

Week of May 15th                                                                                                                                                Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Complete low voltage
Start wall insulation and stock GWB
Begin metal roof insulation
Install window and interior doorframes
Start plaster […]

May 12th, 2017|Learning Spaces|

Tierra Linda/CLC Campus Rebuild Construction Update for 5/8/17-5/21/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/8/2017 through 5/21/2017
 

Week of May 8th                                                                                                                                                 Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include

Continue framing pick-up/punch lists
Continue roofing membrane
Install window and interior doorframes
Finish lath/start stucco

Activities at Modular Multi-Use Room Building

[…]

May 9th, 2017|Learning Spaces|

Tierra Linda/CLC Construction Update 5/1/17 – 5/14/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
5/1/2017 through 5/14/2017
Week of May 1st                                                                                                                                                                    Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Continue framing pick-up/punch lists
Continue roofing membrane
Install window frames
Finish lath/start plaster

Activities at Modular Multi-Use Room Building

Continue […]

Background Narrative and Timeline – Facilities Master Plan (FMP)

I want to invite you to read a new document written and compiled by District Staff. This helpful narrative and timeline was written for parents and community members to learn more about the planning and implementation processes pertaining to our Facilities Master Plan. This document is meant to give context and background […]

April 26th, 2017|Blog, Learning Spaces, News|

Tierra Linda/CLC Campus Construction Update 4/24 – 5/7/2017

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
4/24/2017 through 5/7/2017
 

Week of April 24th                                                                                             

Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:  

Activities at the new Learning Commons will include:

Finish framing pick-up/punch lists
Continue roofing membrane
Install window frames
Begin plaster

Activities at Modular Multi-Use Room Building

Continue ceramic tile
[…]

Tierra Linda/CLC Construction Update foe 4/3-4/16/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
4/3/2017 through 4/16/2017

Week of April 3rd                                                                                             Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Continue framing (north, south, common walls and roof walls) and roof
Stage and install roof decking materials
Continue fire suppression system […]

Tierra Linda/CLC Campus Rebuild Project Construction Update 3/27-4/9/17

Tierra Linda/CLC Campus Rebuild Project
Two Week Look Ahead
3/27/2017 through 4/9/2017
Week of March 27th                                                                                          Work Hours: 8:00 a.m. – 6:00 p.m.

Activities:

Activities at the new Learning Commons will include:

Complete framing (north, south, common walls and roof walls) and roof
Stage decking materials
Shear wall framing and sheeting
Continue fire suppression system […]